Buildings and Facilities19OI0014

CONST. OF M/P BLDG FOR THE PHILIPPINE FIBER INDUSTRY DEV'T. AUTHORITY (PHILFIDA) BLDG, BRGY. TALON 2

CONST. OF M/P BLDG FOR THE PHILIPPINE FIBER INDUSTRY DEV'T. AUTHORITY (PHILFIDA) BLDG, BRGY. TALON 2 is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱57,899,999.45. Status: Reported complete (DPWH). Contractor on record: JQD CONST & GEN SERVICES. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-NCR-19-0003196

₱79,890.00 · FY2019

Released to Division of Muntinlupa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱673.4M total · 4 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS/MAASIN CITY COASTAL BYPASS ROAD, INCL. SLOPE PROTECTION, SOUTHERN LEYTE (CONSTRUCTION OF CONCRETE ROAD AND CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE)MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2018₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS / MAASIN CITY COASTAL BYPASS ROAD, SOUTHERN LEYTE, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2021₱77.2M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - BDRY. SO. LEYTE - MAASIN - MACROHON - SOGOD - JCT. DAANG MAHARLIKA RD. - ALONG MAASIN CITY SECTION

Southern Leyte 1st DEO, Region VIII

2024₱61.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - MULTI-PURPOSE BUILDING / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF LEGISLATIVE BUILDING, TOMAS OPPUS, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱49.5M
Reported complete (DPWH)
No sat.

Construction of Canturing Flood Structures, Canturing River, Maasin City, Southern Leyte

CITY OF MAASIN (CAPITAL) (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII

2023₱49.0M
Reported complete (DPWH)
No sat.

Construction of Canturing River Flood Control, Brgy. Nasaug, Segment 2, Maasin City, Southern Leyte

CITY OF MAASIN (CAPITAL) (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII

2024₱48.9M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱57,899,999.45

Progress

Reported complete (DPWH)

Start Date

July 5, 2019

Target End

May 21, 2022

5. Audit