Roads17IL0056

OPENING/CONSTRUCTION/REHABILITATION OF BRGY. MABICAY-BRGY. SAN PEDRO FMR (STA. 1+000 - STA. 1+620) AND (STA. 1+620 -STA. 3+800), BRGYS. MABICAY AND SAN PEDRO, SOGOD, SOUTHERN LEYTE

OPENING/CONSTRUCTION/REHABILITATION OF BRGY. MABICAY-BRGY. SAN PEDRO FMR (STA. 1+000 - STA. 1+620) AND (STA. 1+620 -STA. 3+800), BRGYS. MABICAY AND SAN PEDRO, SOGOD, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱47,543,099.88. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,122,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Subang Daku Flood Control, San Juan Section , Sta. 9+760 - Sta. 10+400 , San Juan , Sogod , Southern Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0016505

₱3,040,860.00 · FY2017

Released to 000000 - Southern Per hilippines Agri-Business and tea ne and Aquatic School of echnology (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱47,543,099.88

Progress

Reported complete (DPWH)

Start Date

July 18, 2017

Target End

July 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.