Construction of Flood Mitigation Structure24ED0018

Construction of Abaton River Control, Calapan City, Oriental Mindoro

Construction of Abaton River Control, Calapan City, Oriental Mindoro is a DPWH-tracked public work in CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱48,996,963.79. Status: Reported complete (DPWH). Contractor on record: MARTINEZ ENT / FRAMECON BUILDERS. Figures trace to sumbong.

CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Longos River ( Downstream ) , Calapan City, Oriental Mindoro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008378

₱1,267,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004239

₱1,035,174.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001426

₱2,931,832.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008390

₱117,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004240

₱92,822.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001427

₱270,752.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,996,963.79

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

October 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.