ROAD UPGRADING-UNPAVED TO PAVED-ALONG H-WAY JCT. MANA-TICULON-LAGUMIT-LITTLE BAGUIO ROAD TALAUD SECTION, MALITA, DAVAO OCCIDENTAL-KM. 1648+438-KM. 1650+520

ROAD UPGRADING-UNPAVED TO PAVED-ALONG H-WAY JCT. MANA-TICULON-LAGUMIT-LITTLE BAGUIO ROAD TALAUD SECTION, MALITA, DAVAO OCCIDENTAL-KM. 1648+438-KM. 1650+520 is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱37,246,085.78. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment, Davao River Flood Control, Jade Valley Section, Brgy. Tigatto, Davao City 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038857

₱-13,759,448.00 · FY2016

Released to Bukidnon 2n (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱37,246,085.78

Progress

Reported complete (DPWH)

Start Date

April 7, 2016

Target End

August 20, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.