Roads23AH0107

CONCRETING OF BRGY. NIBALIW NARVARTE FMR, BRGY.NIBALIW NARVARTE, SAN FABIAN, PANGASINAN

CONCRETING OF BRGY. NIBALIW NARVARTE FMR, BRGY.NIBALIW NARVARTE, SAN FABIAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 2nd DEO, Region I. Reported contract value: ₱4,968,949.75. Status: Reported complete (DPWH). Contractor on record: MIGHTYWAY CONST AND SUPPLY. Figures trace to dpwh.

Pangasinan 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Located at Barangay San Joaquin, Balungao, Pangasinan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pangasinan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,968,949.75

Progress

Reported complete (DPWH)

Start Date

May 5, 2023

Target End

September 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.