Flood Control and Drainage21LB0290

CONSTRUCTION OF DRAINAGE SYSTEM AT NHA BANGKAL, MATUTUM ST. TO OUTFALL, DAVAO CITY

CONSTRUCTION OF DRAINAGE SYSTEM AT NHA BANGKAL, MATUTUM ST. TO OUTFALL, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Sasa Creek Outfall, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao City DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

December 1, 2021

Target End

April 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.