Construction of Flood Mitigation Structure21OG0138

Construction/Rehabilitation of Flood Control Structures at Lumban Creek, Barangay Matandang Balara, Quezon City

Construction/Rehabilitation of Flood Control Structures at Lumban Creek, Barangay Matandang Balara, Quezon City is a DPWH-tracked public work in QUEZON CITY, National Capital Region. Reported contract value: ₱48,985,157.08. Status: Reported complete (DPWH). Contractor on record: PERRC INC FORMERLY: P E R R C CONST & DEVELOPMENT CORP. Figures trace to sumbong.

QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Structures at Lambakan Creek, Barangay Matandang Balara, Quezon City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010167

₱122,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012590

₱79,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012574

₱69,500,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012588

₱242,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010286

₱42,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011451

₱3,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007322

₱52,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

10 projects · ₱831.2M total · 0 flags

4. Implementation

Contract Amount

₱48,985,157.08

Progress

Reported complete (DPWH)

Start Date

November 10, 2021

Target End

October 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.