Buildings and Facilities17GE0130

CONSTRUCTION OF SCHOOL BUILDINGS FUNDED UNDER 2017 BEFF (BATCH 3) COMPLETION OF ONE STOREY 2CL SCHOOL BUILDING, UMILIG PRIMARY SCHOOL

CONSTRUCTION OF SCHOOL BUILDINGS FUNDED UNDER 2017 BEFF (BATCH 3) COMPLETION OF ONE STOREY 2CL SCHOOL BUILDING, UMILIG PRIMARY SCHOOL is a DPWH-tracked public work in Guimaras DEO, Region VI. Reported contract value: ₱546,125.54. Status: Reported complete (DPWH). Contractor on record: ALJ CONST AND SUPPLY. Figures trace to dpwh.

Guimaras DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tastasan Flood Project, Buenavista, Guimaras
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0012440

₱7,553,738.00 · FY2017

Released to Division of Butuan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱546,125.54

Progress

Reported complete (DPWH)

Start Date

December 16, 2017

Target End

January 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.