Roads21N00157

CONSTRUCTION OF CIRCUMFERENTIAL ROAD ALONG AGUSAN MARSH ROAD, BUNAWAN SECTION (PHASE 5), AGUSAN DEL SUR

CONSTRUCTION OF CIRCUMFERENTIAL ROAD ALONG AGUSAN MARSH ROAD, BUNAWAN SECTION (PHASE 5), AGUSAN DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱125,387,859.40. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC 17267. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱125,387,859.40

Progress

Reported complete (DPWH)

Start Date

January 7, 2022

Target End

June 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.