Roads21FB0178

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS LEGAZPI CITY-PUNTA DE JESUS RD - K0556 + 463 - K0556 + 630

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS LEGAZPI CITY-PUNTA DE JESUS RD - K0556 + 463 - K0556 + 630 is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱12,282,749.62. Status: Past target date (DPWH On-Going). Contractor on record: CBC CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System, Purok 2 Gogon, Legazpi City, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

87 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-ROAD SAFETY FEATURES/DEVICES ALONG NATIONAL ROADS AND BRIDGES-INSTALLATION OF SOLAR STREET LIGHTS ALONG DAANG MAHARLIKA (LZ)-K0555+699-K0571+556

Region V, Region V

2024₱141.1M
Past target date (DPWH On-Going)
No sat.

CSSP:SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ILAWODLIGBAN ROAD DIKE TRIBUTARY CHANNEL, PACKAGE 2, CAMALIG

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DIKE ALONG BARIW TRIBUTARY CHANNEL, PACKAGE 2, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF CAGSAWA FLOOD MITIGATION STRUCTURE ALONG TRIBUTARIES OF BARANGAY BUDIAO TO BARANGAY

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TAGAYTAY-LIBOD ROAD, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS(SIPAG):ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SAN JOAQUIN-PAWA-BOGTONG ROAD LEADING TO LEGAZPI CITY AIRPORT,LEGAZPI,

Albay 2nd DEO, Region V

2024₱91.7M
Past target date (DPWH On-Going)
View all 87 projects →

4. Implementation

Contract Amount

₱12,282,749.62

Progress

Past target date (DPWH On-Going)

Start Date

September 16, 2021

Target End

June 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.