Flood Control and Drainage25C00351

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 2, SAN MIGUEL, BULACAN

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 2, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱95,051,481.18. Status: Past target date (DPWH On-Going). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST 20201. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Meycauayan River and its tributaries (Deca Homes Section), Barangay Saluysoy, Meycauayan City, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱95,051,481.18

Progress

Past target date (DPWH On-Going)

Start Date

March 14, 2025

Target End

January 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.