Flood Control and Drainage24DQ0056

CONSTRUCTION OF SLOPE PROTECTION ALONG IMUS RIVER (TRIBUTARY TO MANILA BAY), PHASE 1, BARANGAY SAN AGUSTIN I, DASMARIÑAS CITY, CAVITE

CONSTRUCTION OF SLOPE PROTECTION ALONG IMUS RIVER (TRIBUTARY TO MANILA BAY), PHASE 1, BARANGAY SAN AGUSTIN I, DASMARIÑAS CITY, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱106,149,993.89. Status: Past target date (DPWH On-Going). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Pob 3, Pob 1, San Vicente I, San Vicente II, Silang, Cavite
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0016076

₱310,523,000.00 · FY2024

Released to Regional Office - III (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

161 projects · ₱8.0B total · 11 flags

4. Implementation

Contract Amount

₱106,149,993.89

Progress

Past target date (DPWH On-Going)

Start Date

May 15, 2024

Target End

December 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.