Buildings and Facilities17IM0056

CONSTRUCTION OF SCHOOL BUILDING STANDARD DPWH THREE STOREY NINE CLASSROOMS, LEYTE NATIONAL HIGH SCHOOL, TACLOBAN CITY

CONSTRUCTION OF SCHOOL BUILDING STANDARD DPWH THREE STOREY NINE CLASSROOMS, LEYTE NATIONAL HIGH SCHOOL, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱16,240,062.09. Status: Reported complete (DPWH). Contractor on record: R T MORABE CONST. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038826

₱-3,074,246.00 · FY2016

Released to Davao Orien (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱16,240,062.09

Progress

Reported complete (DPWH)

Start Date

December 29, 2017

Target End

July 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.