GAA 2025 SSP25DD0324

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING SLOPE PROTEC

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING SLOPE PROTEC is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱9,506,000.00. Status: Past target date (DPWH On-Going). Contractor on record: T SOLOMON CONST AND DEVELOPMENT CORPORATIO. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Calicanto, San Juan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

60 projects · ₱1.6B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD ALONG QUATRO SANTOS R

Batangas 4th DEO, Region IV-A

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANILA - BATANGAS BYPASS ROAD PACKAGE E, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱93.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PANGAO INTEGRATED SCHOOL, BARANGAY PANGAO, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱78.7M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING - SECONDARY ROADS DIOKNO HIGHWAY - K0073+000.00 - K0073+440.00, K0075+577.00 - K0076+303.00

Region IV-A, Region IV-A

2022₱57.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BALETE SECT

Batangas 3rd DEO, Region IV-A

2025₱56.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SITIO STO. TORIBIO ELEMENTARY SCHOOL, BARANGAY

Batangas 4th DEO, Region IV-A

2023₱51.5M
Reported complete (DPWH)
View all 60 projects →

4. Implementation

Contract Amount

₱9,506,000.00

Progress

Past target date (DPWH On-Going)

Start Date

June 9, 2025

Target End

September 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.