Flood Control and Drainage21FO0086

CLUSTER: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAN FRANCISCO RIVER, GUINOBATAN, ALBAY AND CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG SAN FRANCISCO RIVER, GUINOBATAN, ALBAY

CLUSTER: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAN FRANCISCO RIVER, GUINOBATAN, ALBAY AND CONSTRUCTION OF FLOOD MITIGATION SYSTEM ALONG SAN FRANCISCO RIVER, GUINOBATAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱88,199,986.79. Status: Reported complete (DPWH). Contractor on record: HI-TONE CONST & DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Along San Francisco River, Guinobatan, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

175 projects · ₱17.1B total · 0 flags

Other projects by this contractor

No sat.

DESIGN AND BUILD OF COASTAL DIKE AND DRAINAGE IMPROVEMENT, CATBALOGAN CITY, SAMAR

Flood Control Management Cluster, Central Office

2019₱744.4M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTION OF BICOL REGIONAL HOSPITAL AND MEDICAL CENTER (MEDICAL ARTS BUILDING AND FACILITIES, PATIENT'S ROOM AND TRAINING CENTER), DARAGA, ALBAY, DARAGA,

Region V, Region V

2023₱475.3M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTON 0F BICOL UNIVERSITY CONVENTION AND DISASTER RISK REDUCTION MANAGEMENT CENTER, DARAGA, ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱374.4M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BATO LAKESHORE DIKE ROAD(CIRCUMFERENTIAL ROAD) IN SUPPORT OF AGRIC

Region V, Region V

2023₱279.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF COASTAL ROAD AND SHORE P

Region V, Region V

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF NBI BUILDING, REGIONAL OFFICE V, REGIONAL GOVERNMENT CENTER, RAWIS, LEGAZPI, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2023₱241.5M
Past target date (DPWH On-Going)
View all 175 projects →

4. Implementation

Contract Amount

₱88,199,986.79

Progress

Reported complete (DPWH)

Start Date

April 23, 2021

Target End

April 2, 2022

5. Audit