Roads20DD0350

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONCRETING OF LOCAL ROAD, BRGY. SALABAN I, IBAAN, BATANGAS

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONCRETING OF LOCAL ROAD, BRGY. SALABAN I, IBAAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱9,603,000.00. Status: Reported complete (DPWH). Contractor on record: 830 BUILDERS. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structure at Brgy. Tambo, Lipa City, Batangas
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Batangas 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

167 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT AND SITE FACILITIES, PARK AND PLAZA, POBLACION,

Batangas 4th DEO, Region IV-A

2024₱28.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (AUDITORIUM) INCLUDING SITE DEVELOPMENT AT BRGY. DON LUIS, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱28.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF PROVINCIAL ROAD (MAKALINTAL AVENUE), BARANGAYS BANAY

Batangas 4th DEO, Region IV-A

2022₱28.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, BATANGAS-QUEZON RD - K0115 + 587 - K0116 + 000, K0121 + 719 - K0121 +

Batangas 4th DEO, Region IV-A

2025₱28.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BOX CULVERT, ROAD AND ROAD APPROACHES, DRAINAGE SYSTEM, SLOPE PROTECTION AND RELATED STRUCTURES AT BARANGAYS TUGTUG TO NATUNUAN, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2019₱28.1M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, REHABILITATION OF PALANCA-BALAGTASIN- PINAGTUNG ULAN PROVINCIAL ROAD AND ANUS-SABANG PROVINCIAL ROAD, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2019₱24.7M
Reported complete (DPWH)
View all 167 projects →

4. Implementation

Contract Amount

₱9,603,000.00

Progress

Reported complete (DPWH)

Start Date

December 9, 2020

Target End

March 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.