Roads19PA0096

REPAIR/REHABILITATION/IMPROVEMENT OF ANGAD ROAD, ANGAD, BANGUED, ABRA

REPAIR/REHABILITATION/IMPROVEMENT OF ANGAD ROAD, ANGAD, BANGUED, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱9,898,000.00. Status: Reported complete (DPWH). Contractor on record: PHESCO INC 145. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0014890

₱159,955.00 · FY2019

Released to Banquerohan National High School A an (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

342 projects · ₱29.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOOT BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD

Cordillera Administrative Region, Cordillera Administrative Region

2020₱530.8M
Reported complete (DPWH)
No sat.

CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS GOV. BADO DANGWA NATIONAL ROAD (1) K0342 +

Cordillera Administrative Region, Cordillera Administrative Region

2021₱492.1M
Reported complete (DPWH)
No sat.

ROCKFALL NETTING INCLUDING IMPROVEMENT OF CRITICAL INTERSECTION AT JCT. SHRINE HILLS ALONG DAVAO CITY DIVERSION ROAD, MATINA CROSSING, DAVAO CITY

Region XI, Region XI

2021₱333.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO301+(-905) - KO304+024, KO313+175 - KO317+533, KO319+000 - KO322+600, KO324+0

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BENGUET - NUEVA VIZCAYA ROADKO254+(-372) - KO281+800BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2021₱289.5M
Reported complete (DPWH)
No sat.

MT PROV - CAGAYAN VIA TABUK - ENRILE RD, K0406+453 - KO406+692SADANGA, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
View all 342 projects →

4. Implementation

Contract Amount

₱9,898,000.00

Progress

Reported complete (DPWH)

Start Date

September 10, 2019

Target End

December 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.