Roads18J00052

ROAD WIDENING - PRIMARY ROADS - LANAO - PAGADIAN - ZAMBOANGA CITY ROAD

ROAD WIDENING - PRIMARY ROADS - LANAO - PAGADIAN - ZAMBOANGA CITY ROAD is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱157,881,430.20. Status: Reported complete (DPWH). Contractor on record: ALRAF CONST AND ENT INC FORMERLY:ALRAF CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱2.6B total · 0 flags

Other projects by this contractor

No sat.

UPGRADING (GRAVEL TO PAVED) OF JCT TAGASILAY ALONG MCLL HIGHWAY, TAGASILAY - VITALI SECTION LEADING TO MERLOQUET FALLS, VITALI, ZAMBOANGA CITY, 003 + 640.00 TO 09 + 930 (NET LENGTH: 6,290.00 LN.M.)

Region IX, Region IX

2016₱204.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE AT TUMAGA RIVER BASIN (TUMAGA - TUGBUNGAN SECTION) ZAMBOANGA CITY, 0+000 TO 8 + 487.80 (NET LENGTH: 8,487.80 LN.M.)

Region IX, Region IX

2016₱183.8M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL AT TUMAGA RIVER BASIN, TETUAN - TUGBUNGAN SECTION, ZAMBOANGA CITY

Region IX, Region IX

2018₱148.6M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (GRAVEL TO CONCRETE) OF JCT. TAGASILAY ALONG MCLL HIGHWAY TAGASILAY - VITALI SECTION LEADING TO MERLOQUET FALLS, VITALI, ZAMBOANGA CITY, K009+930.00 - K012+842.64 LENGTH: 2,912.64 LN.M., EXCEPTION: 17.18 LN.M. (EXISTING SPILLWAY), ADDITIONA

Region IX, Region IX

2017₱141.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, CABALUAY - ZAMBOWOOD - MAMPANG SECTION, PACKAGE 3, INCLUDING RROW, ZAMBOANGA CITY

Region IX, Region IX

2018₱133.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, CABALUAY - ZAMBOWOOD - MAMPANG SECTION, PACKAGE 2, INCLUDING RROW, ZAMBOANGA CITY

Region IX, Region IX

2018₱124.8M
Past target date (DPWH On-Going)
View all 31 projects →

4. Implementation

Contract Amount

₱157,881,430.20

Progress

Reported complete (DPWH)

Start Date

July 26, 2018

Target End

May 6, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.