Bridges16GG0048

CONSTRUCTION OF BRIDGE, BRGY. CABUNGA, PASSI CITY, ILOILO 4TH LD

CONSTRUCTION OF BRIDGE, BRGY. CABUNGA, PASSI CITY, ILOILO 4TH LD is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱5,854,237.44. Status: Reported complete (DPWH). Contractor on record: SDB STEELSTRUCT BUILDERS ENT. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,854,237.44

Progress

Reported complete (DPWH)

Start Date

April 12, 2016

Target End

August 29, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.