Flood Control and Drainage18OE0055

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTEIS AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE BINONDO, STA. 0+283.56 TO STA. 0+323.96, MANILA CIT

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTEIS AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE BINONDO, STA. 0+283.56 TO STA. 0+323.96, MANILA CIT is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱28,823,863.28. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Bank Improvement (Steel Sheet Pile) Estero de Binondo, Sta. 0+283.56 to Sta. 0+323.96, Manila City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033895

₱0.00 · FY2018

Released to Dacap Norte National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱28,823,863.28

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

August 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.