Buildings and Facilities23DD0044

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY LALAYAT, SAN JOSE, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY LALAYAT, SAN JOSE, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱2,880,953.00. Status: Reported complete (DPWH). Contractor on record: VRV CONST AND TRADING. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Box Culvert, Cultihan Road, Barangay Salaban, San Jose, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

195 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), PADRE GARCIA COMMUNITY HOSPITAL, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱96.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BOLBOK INTEGRATED NATIONAL HIGH SCHOOL, BARANGAY BOLBOK, LIPA CITY, BATA

Batangas 4th DEO, Region IV-A

2024₱78.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TALISAY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION/ COMPLETION OF MULTI-PURPOSE BUILDING (COMMUNITY HOSPITAL) AT BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAXIMO T. HERNANDEZ MEMORIAL NATIONAL HIGH SCHOOL AND MALAININ ELEMENTARY SCHOOL, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI- PURPOSE BUILDING (BUREAU OF FIRE), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.0M
Reported complete (DPWH)
View all 195 projects →

4. Implementation

Contract Amount

₱2,880,953.00

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

April 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.