Buildings and Facilities20HG0023

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM; BUILDINGS AND OTHER STRUCTURES; MULTIPURPOSE/FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BASDIOT ELEM. SCHOOL, BRGY. BASDIOT, MOALBOAL, CEBU

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM; BUILDINGS AND OTHER STRUCTURES; MULTIPURPOSE/FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BASDIOT ELEM. SCHOOL, BRGY. BASDIOT, MOALBOAL, CEBU is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱968,998.25. Status: Reported complete (DPWH). Contractor on record: WORLDWIDE BUILDERS. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

256 projects · ₱2.1B total · 4 flags

Other projects by this contractor

Construction of Dike along Kabalaasnan River, Dumanjug, Cebu

DUMANJUG (CEBU), CEBU, Region VII

2023₱96.5M
Reported complete (DPWH)

Construction of River Retaining Wall Structure at Sitio Upper Talayong, Barangay Tupas, Ronda, Cebu (Upstream)

RONDA (CEBU), CEBU, Region VII

2023₱96.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF RIVER CHANNEL IMPROVEMENT ALONG SITIO UPPER TALAYONG - SITIO LOWER T

Cebu 7th DEO, Region VII

2023₱75.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE - CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION/FLOOD MITIGATION STRUCTURE, BARANGAY PANALIPAN, CATMON, CEBU

Cebu 5th DEO, Region VII

2021₱71.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL DIKE AT BARANGAY KABALAASNAN (DOWNST

Cebu 7th DEO, Region VII

2024₱70.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, PUROK LUBE, BARANGAY KABALAASNAN (DOWNSTR

Cebu 7th DEO, Region VII

2025₱70.9M
Past target date (DPWH On-Going)
View all 256 projects →

4. Implementation

Contract Amount

₱968,998.25

Progress

Reported complete (DPWH)

Start Date

February 12, 2020

Target End

May 30, 2020

5. Audit