Roads24B00081

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SIGNAGE-WARNING, ADVISORY AND REGULATORY SIGNS, PAVEMENT MARKINGS, AND STREET LIGHTS ALONG DAANG MAHARLIKA (LZ) (S00852LZ)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SIGNAGE-WARNING, ADVISORY AND REGULATORY SIGNS, PAVEMENT MARKINGS, AND STREET LIGHTS ALONG DAANG MAHARLIKA (LZ) (S00852LZ) is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱1,071,525.18. Status: Reported complete (DPWH). Contractor on record: JANN-NORRIS CONST AND SUPPLIES INC FORMELY: JANN-NORRIS CONST AND SUPPLIES. Figures trace to dpwh.

Region II, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

247 projects · ₱10.9B total · 0 flags

Other projects by this contractor

No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BAYOMBONG-SOLANO BY-PASS ROAD, BAYOMBONG - SOLANO, NUEVA VIZCAYA

Region II, Region II

2019₱238.9M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0292 + 000 - K0293 + 225, K0293 + 356 - K0294 + 100, K0294 + 152 - K

Region II, Region II

2024₱196.4M
Past target date (DPWH On-Going)
No sat.

CAPITAL OUTLAY-NATIONAL BRIDGE CONST'N/REPLACEMENT PROGRAM CONST'N OF MADDIANGAT BRIDGE AND APPROACHES INCLUDING RIGHT-OF-WAY ACQUISITION ALONG BAMBANG KASIBU-QUEZON-SOLANO ROAD, NUEVA VIZCAYA

Region II, Region II

2017₱194.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG MANILA NORTH RD, - K0590+(-784) - K0593+608; K0593+637-K0595+000; K064

Region II, Region II

2024₱184.3M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NAT'L ROAD SYSTEM: NETWORK DEV'T PROGRAM: ROAD WIDENING-PRIMARY ROADS ALONG DAANG MAHARLIKA (LZ),K0254+641-K0255+K249.50, K0259+899.20 - K0260+ 051.7 , K0260+072.30 - K0260+225.70, K0261+090 - K0261+242,QUIRINO LONE DISTRICT

Region II, Region II

2018₱165.2M
Reported complete (DPWH)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEV'T: ROAD WIDENING PRIMARY ROAD ALONG DAANG MAHARLIKA, K0216+886 K0219+092.70 = STA. 216+781-STA. 219+092.70, K0219+224-K0219+899 = STA. 219+138.70-STA. 219+813.70, STA. FE, NUEVA VIZCAYA

Region II, Region II

2018₱161.1M
Reported complete (DPWH)
View all 247 projects →

4. Implementation

Contract Amount

₱1,071,525.18

Progress

Reported complete (DPWH)

Start Date

July 12, 2024

Target End

August 18, 2024

5. Audit