Construction of Flood Mitigation Structure22GP0070

Construction of River Control along Panay River Basin, Sitio Ilaya Proper, Brgy. Atiplo, Mambusao, Capiz

Construction of River Control along Panay River Basin, Sitio Ilaya Proper, Brgy. Atiplo, Mambusao, Capiz is a DPWH-tracked public work in MAMBUSAO (CAPIZ), CAPIZ, Region VI. Reported contract value: ₱55,969,403.95. Status: Reported complete (DPWH). Contractor on record: SUPREME ABF CONST & CONST SUPPLY CO INC. Figures trace to sumbong.

MAMBUSAO (CAPIZ), CAPIZ, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Visayan Sea (Phase 2), Brgy. Punta Cogon, Roxas City, Capiz
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002966

₱133,142,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

68 projects · ₱5.3B total · 2 flags

4. Implementation

Contract Amount

₱55,969,403.95

Progress

Reported complete (DPWH)

Start Date

March 6, 2022

Target End

November 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.