Construction of Drainage Structure22CF0011

Construction of Drainage, Peñaranda, Nueva Ecija

Construction of Drainage, Peñaranda, Nueva Ecija is a DPWH-tracked public work in PEÑARANDA (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱7,840,925.62. Status: Reported complete (DPWH). Contractor on record: NIVIN DEVELOPMENT CONST CORP. Figures trace to sumbong.

PEÑARANDA (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Barangay Buliran, San Antonio, Nueva Ecija
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002910

₱344,535,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001720

₱52,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002804

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001627

₱15,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003016

₱10,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,840,925.62

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

July 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.