Bridges20CC0114

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - LABANGAN BRIDGE 7 (B00148LZ) ALONG MANILA NORTH ROAD CALUMPIT, BULACAN

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - LABANGAN BRIDGE 7 (B00148LZ) ALONG MANILA NORTH ROAD CALUMPIT, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱47,040,530.01. Status: Reported complete (DPWH). Contractor on record: LE BRON CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Brgy. Balungao, Calumpit, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

249 projects · ₱16.0B total · 11 flags

4. Implementation

Contract Amount

₱47,040,530.01

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

June 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.