Buildings and Facilities22CC0320

CONSTRUCTION (COMPLETION) OF TECHNICAL BUILDING, BULACAN 1ST DEO, DPWH COMPOUND, TIKAY, MALOLOS CITY, BULACAN

CONSTRUCTION (COMPLETION) OF TECHNICAL BUILDING, BULACAN 1ST DEO, DPWH COMPOUND, TIKAY, MALOLOS CITY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: TBB CONST CORP. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Calizon, Calumpit, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bulacan 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

May 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.