Roads23DP0031

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0074 + 290 - K0074 + 670

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0074 + 290 - K0074 + 670 is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱12,962,621.23. Status: Reported complete (DPWH). Contractor on record: BHENLLABIEN BUILDERS CORP FORMERLY: BHENLLABIEN BUILDERS CONST. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Malaban, Bi±an City, Laguna
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Laguna 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱12,962,621.23

Progress

Reported complete (DPWH)

Start Date

September 14, 2023

Target End

January 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.