Roads17OF0048

CONSTRUCTION AND REHABILITATION OF D. TUAZON STREET, BRGY. LOURDES, Q.C.

CONSTRUCTION AND REHABILITATION OF D. TUAZON STREET, BRGY. LOURDES, Q.C. is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱18,314,994.57. Status: Reported complete (DPWH). Contractor on record: AQUATERRA KONSTRUKT INC. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure and Tributaries at Brgy. Bagong Silangan, Quezon City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

19 projects · ₱454.0M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM-WATER SUPPLY - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2022₱69.2M
Reported complete (DPWH)
No sat.

CONST/REP/REHAB/IMPR OF VARIOUS INFRA INCL LOCAL PROJ-WATER SUPPLY-CONST OF WATER SUPPLY PROJ, PANAY

Capiz 1st DEO, Region VI

2017₱55.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱44.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUMAGA RIVER BASIN AT PASONANCA-LUYAHAN SECTION (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY 1ST LD

Zamboanga City 2nd DEO, Region IX

2016₱43.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM-WATER SUPPLY - CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2022₱42.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION / REHABILITATION OF WATER SUPPY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SUPPLY SYSTEMS - CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BALBAL

Upper Kalinga DEO, Cordillera Administrative Region

2024₱34.3M
Reported complete (100% progress, DPWH status On-Going)
View all 19 projects →

4. Implementation

Contract Amount

₱18,314,994.57

Progress

Reported complete (DPWH)

Start Date

April 12, 2017

Target End

April 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.