Buildings and Facilities17KH0079

CONSTRUCTION OF CLASSROOMS: 3STY12CL PAGATPAT ES, BRGY. PAGATPAT, CAGAYAN DE ORO CITY

CONSTRUCTION OF CLASSROOMS: 3STY12CL PAGATPAT ES, BRGY. PAGATPAT, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Cagayan de Oro City 1st DEO, Region X. Reported contract value: ₱28,867,785.60. Status: Reported complete (DPWH). Contractor on record: JIMWEN CONST. Figures trace to dpwh.

Cagayan de Oro City 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood River Control at Barangay Baloy to Barangay Tablon, Cagayan de Oro City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0010836

₱277,253.00 · FY2017

Released to Salvacion National High School - Bato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

315 projects · ₱2.7B total · 0 flags

4. Implementation

Contract Amount

₱28,867,785.60

Progress

Reported complete (DPWH)

Start Date

January 15, 2018

Target End

October 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.