Construction of Flood Mitigation Structure21PC0019

Construction of Cabicungan Flood Control Structure, Sta. 13 + 580 - Sta. 13 + 605 (L/S), Sta 13+180-Sta 13+280 (L/S), Sta 13+460-Sta 13+510 (R/S), Sta 13+230-Sta 13+430 (R/S), Calanasan, Apayao

Construction of Cabicungan Flood Control Structure, Sta. 13 + 580 - Sta. 13 + 605 (L/S), Sta 13+180-Sta 13+280 (L/S), Sta 13+460-Sta 13+510 (R/S), Sta 13+230-Sta 13+430 (R/S), Calanasan, Apayao is a DPWH-tracked public work in APAYAO, Cordillera Administrative Region. Reported contract value: ₱47,521,251.30. Status: Reported complete (DPWH). Contractor on record: ASC CONST & CONCRETE PRODUCTS. Figures trace to sumbong.

APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabicungan Flood Control Structure, Sta. 13 + 580 - Sta. 13 + 605 (L/S), Sta 13+180-Sta 13+280 (L/S), Sta 13+460-Sta 13+510 (R/S), Sta 13+230-Sta 13+430 (R/S), Calanasan, Apayao
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012582

₱118,391,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012564

₱40,000,000.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱47,521,251.30

Progress

Reported complete (DPWH)

Start Date

December 1, 2021

Target End

August 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.