GAA 2025 SSP25FG0067

CONSTRUCTION OF SAGÑAY RIVER FLOOD MITIGATION STRUCTURE, BRGY. BURACAN, SAGÑAY, CAMARINES SUR

CONSTRUCTION OF SAGÑAY RIVER FLOOD MITIGATION STRUCTURE, BRGY. BURACAN, SAGÑAY, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱95,039,976.87. Status: Past target date (DPWH On-Going). Contractor on record: ALRO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Harrison, Garchitorena, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

91 projects · ₱5.7B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, BRGY. BUDIAO, DARAGA, ,ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱184.5M
Past target date (DPWH On-Going)

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, UPSTREAM OF CAMALIG BRIDGE, BRGY. 4 (POB)-QUIRANGAY, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱159.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY BATANG, IROSIN, SORSOGON

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GABAO RIVER, BARANGAY GABAO

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱154.3M
Past target date (DPWH On-Going)
View all 91 projects →

4. Implementation

Contract Amount

₱95,039,976.87

Progress

Past target date (DPWH On-Going)

Start Date

July 8, 2025

Target End

May 11, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.