Roads21CJ0141

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG ACCESS ROAD LEADING TO DUEG ECOTOURISM NATURE'S PARK (PHASE 1), SAN CLEMENTE, TARLA

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG ACCESS ROAD LEADING TO DUEG ECOTOURISM NATURE'S PARK (PHASE 1), SAN CLEMENTE, TARLA is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱93,508,136.27. Status: Reported complete (DPWH). Contractor on record: LOUREL DEVELOPMENT CORP FORMERLY :LOUREL D. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱43,516,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Moriones River Right Bank Including Road Component, Balanti Section (Phase V), Sta. 0+000 - Sta. 0+421, Balanti, Tarlac City, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Tarlac DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

16 projects · ₱1.5B total · 0 flags

4. Implementation

Contract Amount

₱93,508,136.27

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

January 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.