Flood Control and Drainage19BH0014

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF ECHAGUE FLOOD CONTROL PROJECT

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF ECHAGUE FLOOD CONTROL PROJECT is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱39,200,000.00. Status: Reported complete (DPWH). Contractor on record: JC PALOMO CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-19-0000458

₱-139,647,552.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

95 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG-LINAO-ATULUYANBAGAY-BUNTUN), PACKAGE 1, CAGAYAN

Region II, Region II

2024₱149.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN JOSE-QUIBAL ROAD, PACKAGE 1, CAGAYAN

Region II, Region II

2022₱115.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 1, CAGAYAN

Region II, Region II

2023₱106.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS -TUGUEGARAO WEST DIVERSION ROAD (JCT. CARIG - LINAO - ATULAYAN - BAGAY - BUNTUN), PACKAGE 3, CAGAYAN

Region II, Region II

2023₱100.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF MISSING LINKS/NEW ROADS: SAN JOSE-QUIBAL ROAD, PACKAGE 2, CAGAYAN

Region II, Region II

2022₱100.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN-AFUSING RD PHASE III

Cagayan 3rd DEO, Region II

2024₱96.4M
Past target date (DPWH On-Going)
View all 95 projects →

4. Implementation

Contract Amount

₱39,200,000.00

Progress

Reported complete (DPWH)

Start Date

September 16, 2019

Target End

April 4, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.