Flood Control and Drainage16DJ0027

CONSTRUCTION OF REVETMENT, MANGGALANG BANTILAN, SARIAYA, QUEZON 2ND LD

CONSTRUCTION OF REVETMENT, MANGGALANG BANTILAN, SARIAYA, QUEZON 2ND LD is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱1,980,000.00. Status: Reported complete (DPWH). Contractor on record: TANTUCO CONST. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/ Improvement of Flood Control Structures at Mayon Street,District I, Quezon City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0020569

₱358,949.00 · FY2016

Released to 00 - Don Mariano Marcos Memorial State University To cover re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

26 projects · ₱218.6M total · 0 flags

Other projects by this contractor

No sat.

FY 2021 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE AND SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY CONSTRUCTION OF AFP STAFF HOUSE BUILDING I, SOLCOM, LUCENA CITY, QUEZON

Region IV-A, Region IV-A

2021₱49.9M
Reported complete (DPWH)
No sat.

CY 2018 BASIC EDUCATION FACILITIES FUND, (CONSTRUCTION OF CLASSROOMS) BATCH 3, CONSTRUCTION OF CLASSROOMS 2STY 10CLTAGKAWAYAN NHS, TAGKAWAYAN, QUEZON

Quezon 4th DEO, Region IV-A

2018₱24.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ADMINISTRATION BUILDING, HEADQUARTERS, CAMP GUILLERMO NAKAR, LUCENA CITY, QUEZON, PHASE V

Region IV-A, Region IV-A

2024₱18.7M
Past target date (DPWH On-Going)
No sat.

CLUSTER 4-A. CONC. OF SAN PEDRO FMR, BRGY. SAN PEDRO, TIAONG, QUEZON B. CONC. OF BEHIA FMR, BRGY. BEHIA, TIAONG, QUEZON C. CONC. OF SAN FRANCISCO FMR, BRGY. SAN FRANCISCO, TIAONG, QUEZON D. CONC. OF ANASTACIA FMR, BRGY. ANASTACIA, TIAONG, QUEZON E. CONCRE

Quezon 2nd DEO, Region IV-A

2016₱15.8M
Reported complete (DPWH)
No sat.

CLUSTER 6-A. CONC. OF SITIO ILAYA FMR, BRGY. SAN MATEO, DOLORES, QUEZON B. CONC. OF PUROK 1-2 FMR, BRGY. ANTONINO, DOLORES, QUEZON C. CONC. OF PUROK 1 FMR, BRGY. ANTONINO, DOLORES, QUEZON D. CONC. OF SITIO BANGKONG KAHOY FMR, BRGY. KINABUHAYAN, DOLORES, Q

Quezon 2nd DEO, Region IV-A

2016₱15.3M
Reported complete (DPWH)
No sat.

CLUSTER 3-A. CONC. OF GIBANGA FMR, BRGY. GIBANGA, SARIAYA, QUEZON B. CONC. OF TALAAN PANTOC FMR, BRGY. TALAAN PANTOC, SARIAYA, QUEZON C. CONC. OF MANGGALANG KILING FMR, BRGY. MANGGALANG KILING, SARIAYA, QUEZON D. CONC. OF MORONG FMR, BRGY. MORONG, SARIAY

Quezon 2nd DEO, Region IV-A

2016₱13.9M
Reported complete (DPWH)
View all 26 projects →

4. Implementation

Contract Amount

₱1,980,000.00

Progress

Reported complete (DPWH)

Start Date

June 22, 2016

Target End

September 4, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.