Construction of Drainage Structure24DC0029

Construction of Drainage Canal, Barangay Poblacion 1, Laurel, Batangas

Construction of Drainage Canal, Barangay Poblacion 1, Laurel, Batangas is a DPWH-tracked public work in LAUREL (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱4,949,382.55. Status: Reported complete (DPWH). Contractor on record: NDA BUILDERS AND DEVELOPERS. Figures trace to sumbong.

LAUREL (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Tubuan, Lemery, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0014111

₱4,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008409

₱124,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008408

₱1,346,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0000606

₱538,743.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Possible match · 77%

Construction of Drainage System & Other Structure

₱503,404.30 · NDA BUILDERS AND DEVELOPERS

Possible match · 76%

Construction and labor

₱60,000.00 · NDA BUILDERS AND DEVELOPERS

Contractor

101 projects · ₱1.3B total · 2 flags

Other projects by this contractor

View all 101 projects →

4. Implementation

Contract Amount

₱4,949,382.55

Progress

Reported complete (DPWH)

Start Date

April 29, 2024

Target End

August 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.