Flood Control and Drainage23Z00005

CONSTRUCTION OF TWO (2) PUMPING STATION ALONG NAVOTAS COASTAL DIKE (PHASE 6), NAVOTAS CITY

CONSTRUCTION OF TWO (2) PUMPING STATION ALONG NAVOTAS COASTAL DIKE (PHASE 6), NAVOTAS CITY is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱250,851,621.09. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MSB VITUG CONST 33019. Figures trace to dpwh.

Flood Control Management Cluster, Central Office
Region: Central Office

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 33019

29 projects · ₱5.8B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG UGUIS RIVER, BRGY. UGUIS AND ALONG TIBANGRAN RIVER, BRGY. BARANGOBONG, MUNICIPALITY OF NUEVA ERA, ILOCOS NORTE

Flood Control Management Cluster, Central Office

2019₱715.1M
Past target date (DPWH On-Going)
No sat.

PASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 2 AND 3 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER UPSTREAM OF MARIKINA BRIDGE) STA. 14+100 TO STA. 15+450, LEFT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2017₱714.7M
Past target date (DPWH On-Going)
No sat.

PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS)

National Capital Region, National Capital Region

2019₱502.3M
Past target date (DPWH On-Going)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY, DRAINAGE SYSTEM, CATBALOGAN CITY, INCLUDING ANTIAO RIVER CONTROL, SAMAR PROVINCE

Flood Control Management Cluster, Central Office

2018₱445.3M
Reported complete (DPWH)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY DRAINAGE SYSTEM, CATBALOGAN CITY INCLUDING ANTIAO RIVER CONTROL, SAMAR

Flood Control Management Cluster, Central Office

2016₱438.8M
Reported complete (DPWH)
No sat.

AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R

Flood Control Management Cluster, Central Office

2017₱363.2M
Reported complete (100% progress, DPWH status On-Going)
View all 29 projects →

4. Implementation

Contract Amount

₱250,851,621.09

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

September 15, 2023

Target End

May 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.