AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R
AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱363,217,253.32. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MSB VITUG CONST. Figures trace to dpwh.
Total Contract Cost