GAA 2017 MFO-217Z00003

AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R

AGNO RIVER BASIN FLOOD CONTROL PROJECT (PHASE1)-CONSTRUCTION OF PROTECTION WORKS USING GABIONS AND MATTRESSES. BRGY. DORONGAN SAWAT, STA. 2+840 TO STA.3+140 AND STA. 3+140 T0 STA. 3+640, DORONGAN KETAKET, STA 1+592 TO STA. 2+840 MANGATAREM; (PHASE II-A)-R is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱363,217,253.32. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MSB VITUG CONST. Figures trace to dpwh.

Flood Control Management Cluster, Central Office
Region: Central Office

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

32 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG UGUIS RIVER, BRGY. UGUIS AND ALONG TIBANGRAN RIVER, BRGY. BARANGOBONG, MUNICIPALITY OF NUEVA ERA, ILOCOS NORTE

Flood Control Management Cluster, Central Office

2019₱715.1M
Past target date (DPWH On-Going)
No sat.

PASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 2 AND 3 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER UPSTREAM OF MARIKINA BRIDGE) STA. 14+100 TO STA. 15+450, LEFT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2017₱714.7M
Past target date (DPWH On-Going)
No sat.

PROPOSED MANILA BAY REHABILITATION PROGRAM (DREDGING AND DISPOSAL OF SOLID WASTE OR SLUDGE WASTE USING OCEAN-BASED METHODOLOGY INCLUDING CONSTRUCTION/EXTENSION OF THREE (3) DRAINAGE OUTFALLS)

National Capital Region, National Capital Region

2019₱502.3M
Past target date (DPWH On-Going)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY, DRAINAGE SYSTEM, CATBALOGAN CITY, INCLUDING ANTIAO RIVER CONTROL, SAMAR PROVINCE

Flood Control Management Cluster, Central Office

2018₱445.3M
Reported complete (DPWH)

CONSTRUCTION/IMPROVEMENT OF CATBALOGAN CITY DRAINAGE SYSTEM, CATBALOGAN CITY INCLUDING ANTIAO RIVER CONTROL, SAMAR

Flood Control Management Cluster, Central Office

2016₱438.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF GENERAL TRIAS RETARDING BASIN II (YLANG-YLANG RIVER) UNDER THE FLOOD RISK MANAGEMENT FOR YLANG-YLANG RIVER AND RIO CHICO GRANDE RIVER IN THE PROVINCE OF CAVITE INCLUDING ROW

Flood Control Management Cluster, Central Office

2017₱350.2M
Past target date (DPWH On-Going)
View all 32 projects →

4. Implementation

Contract Amount

₱363,217,253.32

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 20, 2017

Target End

March 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.