Roads24CI0040

INSTALLATION OF ROAD SAFETY DEVICES AND FACILITIES ALONG MANILA NORTH RD (S04206LZ)-K0085+573-K0086+345, BARANGAY DAU, MABALACAT, PAMPANGA

INSTALLATION OF ROAD SAFETY DEVICES AND FACILITIES ALONG MANILA NORTH RD (S04206LZ)-K0085+573-K0086+345, BARANGAY DAU, MABALACAT, PAMPANGA is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱9,641,472.11. Status: Reported complete (DPWH). Contractor on record: NEZIAH BUILDERS AND TRADING CORP. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure with Road Dike along Sabangbalen River Phase 1, Mabalacat City, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Pampanga 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱335.7M total · 1 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALASAS CREEK (PHASE III), BARANGAY SAN AGUSTIN, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱49.0M
Reported complete (DPWH)
No sat.

FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SAPANGBALEN RIVER, DOWNSTREAM OF SAPANGBALEN BRIDGE (LEFT DIKE), PHASE II, MABALACAT CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2024₱48.2M
Reported complete (DPWH)
No sat.

FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SAPANG BALEN RIVER, DOWNSTREAM OF SAPANG BALEN BRIDGE (LEFT DIKE), PHASE I, MABALACAT CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2024₱48.2M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENENCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAPANGBALEN RIVER, SITIO PITABACAN, BARANGAY SAN ILDEFONSO, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱38.6M
Reported complete (DPWH)
No sat.

Construction of Reinforced Concrete Slope Protection with Steel Sheet Piles Foundation along Abacan River, Brgy. Amsic to Brgy. Anunas, Angeles City, Pampanga Phase 1

ANGELES CITY (PAMPANGA), PAMPANGA, Region III

2023₱29.2M
Reported complete (DPWH)
No sat.

Repair/Improvement of Reinforced Concrete Slope Protection along Sapang Balen Creek, Sitio Pitabacan, Brgy. San Ildefonso, Magalang, Pampanga

MAGALANG (PAMPANGA), PAMPANGA, Region III

2023₱26.3M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱9,641,472.11

Progress

Reported complete (DPWH)

Start Date

April 2, 2024

Target End

May 16, 2024

5. Audit