Buildings and Facilities18OB0470

CONSTRUCTION OF FOUR (4) STOREY, TWENTY (20) CLASSROOM, SCHOOL BUILDING AT EULOGIO RODRIGUEZ INTEGRATED SCHOOL, BRGY. HAGDAN BATO, MANDALUYONG CITY

CONSTRUCTION OF FOUR (4) STOREY, TWENTY (20) CLASSROOM, SCHOOL BUILDING AT EULOGIO RODRIGUEZ INTEGRATED SCHOOL, BRGY. HAGDAN BATO, MANDALUYONG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱48,051,764.47. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱11,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Palingon River Drainage Outfall, Brgy. Palingon, Taguig City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0026815

₱450,000.00 · FY2018

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,051,764.47

Progress

Reported complete (DPWH)

Start Date

December 28, 2018

Target End

September 17, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.