Construction of Flood Mitigation Structure22FG0010

Construction of Flood Control System of Mahaba Creek leading to Tambang River, Sitio Palayan, Brgy. Lamon, Goa, Camarines Sur

Construction of Flood Control System of Mahaba Creek leading to Tambang River, Sitio Palayan, Brgy. Lamon, Goa, Camarines Sur is a DPWH-tracked public work in GOA (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: SPRING STAR CONST AND SUPPLY. Figures trace to sumbong.

GOA (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System of Mahaba Creek leading to Tambang River, Sitio Palayan, Brgy. Lamon, Goa, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002964

₱353,891,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

225 projects · ₱6.8B total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BALUD NATIONAL ROAD CONNECTING BARANG

Masbate 2nd DEO, Region V

2023₱135.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - C0NSTRUCTION/IMPROVEMENT OF ACCESS OF ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - BALUD - PALANI - PANUBIGAN - PAJO -TALISAY ROAD LEADING TO PALANI BEACHES, PANUBIGA

Masbate 2nd DEO, Region V

2023₱115.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANDAON - DAYHAGAN ROAD, PACKAGE 1, MASBATE

Masbate 2nd DEO, Region V

2024₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS, MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA.5+101 - STA.6+245, AROROY, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MANDAON - DAYHAGAN - ROAD, STA.4+350 - STA.5+750, MANDAON, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA. 3+892 - STA. 5+052, NET LENGTH = 2.320 LANE KM (1.160 KM), AROROY, MASBATE

Masbate 2nd DEO, Region V

2021₱96.5M
Reported complete (DPWH)
View all 225 projects →

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

February 15, 2022

Target End

August 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.