Roads22OA0045

REHABILITATION OF ROAD AT NORTHBAY BOULEVARD (C3 TO MARALA BRIDGE) (PHASE 2), BARANGAY NORTH BAY BOULEVARD SOUTH, NAVOTAS CITY

REHABILITATION OF ROAD AT NORTHBAY BOULEVARD (C3 TO MARALA BRIDGE) (PHASE 2), BARANGAY NORTH BAY BOULEVARD SOUTH, NAVOTAS CITY is a DPWH-tracked public work in Malabon-Navotas DEO, National Capital Region. Reported contract value: ₱4,949,113.76. Status: Reported complete (DPWH). Contractor on record: C B TAMPENGCO CONST. Figures trace to dpwh.

Malabon-Navotas DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Floodwall along Chungkang River (Phase 2), Navotas City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Malabon-Navotas DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

108 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱4,949,113.76

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

May 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.