Flood Control Structures, Roads18L00110

DAVAO CITY COASTAL BYPASS RD AT JCT. DAVAO-COTABATO RD-BAGO APLAYA-TALOMO-MATINA APLAYA-ROXAS AVE.-S

DAVAO CITY COASTAL BYPASS RD AT JCT. DAVAO-COTABATO RD-BAGO APLAYA-TALOMO-MATINA APLAYA-ROXAS AVE.-S is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱352,144,084.45. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱352,144,084.45

Progress

Reported complete (DPWH)

Start Date

October 1, 2018

Target End

December 14, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.