Flood Control and Drainage20FN0083

LOCAL INFRASTRUCTURE PROGRAM FLOOD CONTROL AND DRAINAGE DRAINAGE/PROTECTION WORKS REHABILITATION AT BARIT RIVER, UPSTREAM, MAMPUAG BRIDGE,STA. 0+059.00 - STA. 0+455.00 (RIGHT SIDE)

LOCAL INFRASTRUCTURE PROGRAM FLOOD CONTROL AND DRAINAGE DRAINAGE/PROTECTION WORKS REHABILITATION AT BARIT RIVER, UPSTREAM, MAMPUAG BRIDGE,STA. 0+059.00 - STA. 0+455.00 (RIGHT SIDE) is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱48,014,833.60. Status: Reported complete (DPWH). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Waras River, Diversion Road - San Antonio - Sta. Lucia, Nabua, Camrines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Sur 5th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20FN0083

₱48,014,833.60 · CENTERWAYS CONSTRUCTION AND DEVELOPMENT .

Contractor

C

309 projects · ₱22.7B total · 8 flags

4. Implementation

Contract Amount

₱48,014,833.60

Progress

Reported complete (DPWH)

Start Date

December 7, 2020

Target End

August 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.