Flood Control and Drainage23C00351

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRAS./FACILITIES - CONSTRUCTION OF SLOPE PROTECTION, SAN ILDEFONSO PUBLIC MARKET CREEK, SAN ILDEFONSO, BULACAN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRAS./FACILITIES - CONSTRUCTION OF SLOPE PROTECTION, SAN ILDEFONSO PUBLIC MARKET CREEK, SAN ILDEFONSO, BULACAN is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱19,009,058.64. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BCC BUILDERS AND CONST SUPPLIES CORP. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,009,058.64

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

January 9, 2024

Target End

July 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.