GAA 2025 OO-225A00421

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF STA. MARIA FLOOD CONTROL, STA. MARIA, ILOCOS SUR

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF STA. MARIA FLOOD CONTROL, STA. MARIA, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱28,078,414.91. Status: Past target date (DPWH On-Going). Contractor on record: MBB CONST AND SUPPLY FORMERLY: MBB CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

75 projects · ₱1.4B total · 2 flags

Other projects by this contractor

View all 75 projects →

4. Implementation

Contract Amount

₱28,078,414.91

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2025

Target End

November 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.