Buildings and Facilities23BK0119

CONSTRUCTION OF 1STY2CL, EDEN INTEGRATED SCHOOL, CABARROGUIS, QUIRINO

CONSTRUCTION OF 1STY2CL, EDEN INTEGRATED SCHOOL, CABARROGUIS, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱4,745,017.19. Status: Reported complete (DPWH). Contractor on record: JURIS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

59 projects · ₱362.8M total · 0 flags

Other projects by this contractor

View all 59 projects →

4. Implementation

Contract Amount

₱4,745,017.19

Progress

Reported complete (DPWH)

Start Date

August 16, 2023

Target End

December 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.