Roads22GA0002

PREVENTIVE MAINTENANCE OF ROAD ALONG AKLAN EAST ROAD (S00322PN)K0285+820 K0285+950, K0300+610 K0300+640, K0300+720 K0300+743, K0300+870 K0300+893, K0302+065 K0302+092, K0308+305 K0308+458, K0309+691 K0309+750 AKLAN EAST ROAD

PREVENTIVE MAINTENANCE OF ROAD ALONG AKLAN EAST ROAD (S00322PN)K0285+820 K0285+950, K0300+610 K0300+640, K0300+720 K0300+743, K0300+870 K0300+893, K0302+065 K0302+092, K0308+305 K0308+458, K0309+691 K0309+750 AKLAN EAST ROAD is a DPWH-tracked public work in Aklan DEO, Region VI. Reported contract value: ₱5,557,009.53. Status: Reported complete (DPWH). Contractor on record: FIRST MAKEEN CONST. Figures trace to dpwh.

Aklan DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control along Agbago-Aslum River, Ibajay, Aklan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Aklan DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

264 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱5,557,009.53

Progress

Reported complete (DPWH)

Start Date

March 16, 2022

Target End

June 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.