GAA 2025 DA FMR25NE0040

CONCRETING OF P3 LUNA TO SITIO BUNGA LUNA FMR, SAN JOSE, DINAGAT ISLANDS

CONCRETING OF P3 LUNA TO SITIO BUNGA LUNA FMR, SAN JOSE, DINAGAT ISLANDS is a DPWH-tracked public work in Dinagat Islands DEO, Region XIII. Reported contract value: ₱14,745,934.20. Status: Past target date (DPWH On-Going). Contractor on record: ATJ BUILDERS. Figures trace to dpwh.

Dinagat Islands DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

11 projects · ₱93.8M total · 0 flags

4. Implementation

Contract Amount

₱14,745,934.20

Progress

Past target date (DPWH On-Going)

Start Date

April 15, 2025

Target End

October 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.