GAA 2025 OO-225P00018

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CHICO RIVER BASIN, GANGAT SECTION, STA. 39+001 - STA. 40+076 (R/S), BARANGAY CALAFUG, CONNER, APAYAO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CHICO RIVER BASIN, GANGAT SECTION, STA. 39+001 - STA. 40+076 (R/S), BARANGAY CALAFUG, CONNER, APAYAO is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱95,016,104.77. Status: Past target date (DPWH On-Going). Contractor on record: RODEKOM GEN CONST AND ENT. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱6.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF ROAD, KAPANGAN, BENGUET - SAN GABRIEL, LA UNIONKAPANGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱197.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLI

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETSABLAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱173.6M
Reported complete (DPWH)

Construction of Flood Control Structure along Baroro River, Barangay Bacsil, Bacnotan, LaUnion

BACNOTAN (LA UNION), LA UNION, Region I

2024₱154.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 3 (LABEY-LACAMEN SECTION, BOKOD, BENGUET), BENGUET LONE DISTRICT

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱144.8M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱95,016,104.77

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

February 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.